Aniagwu Blames Power Infrastructure Vandalism for Delays in Ndokwa Electricity Project

Delta State Commissioner for Works (Rural Roads) and Public Information, Mr. Charles AniagwuDelta State Commissioner for Works (Rural Roads) and Public Information, Mr. Charles Aniagwu

Yahaya Idris in Asaba

 

The Delta State Commissioner for Works (Rural Roads) and Public Information, Charles Aniagwu, has blamed repeated vandalism of electricity infrastructure for delays in the completion and effective utilisation of some power projects in the Ndokwa axis of the state.

Aniagwu spoke on Arise News’ The Morning Show, explaining that the state government had repeatedly extended a 33KVA electricity line from Abraka towards Kwale to provide power for communities, farms and businesses.

 

According to him, the government has extended the line three times, but vandals have repeatedly removed the cables.

https://globaltimesnigeria.com/2026/08/25/izeze-foostodey-release-15-warri-inmates/

He said the problem extended beyond the main electricity line, noting that transformers, feeder lines and other cables required to distribute electricity to homes and businesses had also been targeted.

 

Oborevwori Intervenes

 

Aniagwu disclosed that Governor Sheriff Oborevwori had personally intervened in the matter by urging community leaders to take responsibility for protecting government infrastructure located in their areas.

 

The commissioner said protecting public infrastructure was essential if the government’s investment in electricity was to translate into improved economic activity and better living standards.

 

He added that another phase of the electricity project was being implemented by the Ministry of Energy.

 

According to him, similar efforts were also being made to tackle electricity challenges in the Isoko axis.

 

Delta Expands Electricity Generation

Aniagwu said the state was also exploring alternative sources of power, particularly its abundant gas resources.

 

He said the government was encouraging investors to establish power-generating facilities at the Kwale Free Trade Zone, where a gas-gathering hub is already operating.

 

“We are not just relying on hydro to provide power. We are also trying as much as possible to take advantage of the enormous gas resources in Delta,” he said.

 

He said electricity generated at the Kwale facility could serve businesses operating within the Special Economic Zone and potentially other parts of the state.

 

Aniagwu also disclosed that Delta had experimented with about 8.5 megawatts of power generation in Asaba, which currently supplies several government establishments.

 

He said the administration was working towards expanding the initiative to private businesses following the liberalisation of the electricity sector.

 

Energy Commission Planned

 

The commissioner further disclosed that the state government was working towards establishing an energy commission to provide the necessary regulatory framework for the sector.

 

He said the broader strategy was aimed at creating an enabling environment capable of attracting investors, supporting businesses and generating employment.

 

Security and Infrastructure as Investment Priorities

 

Aniagwu said the government had prioritised roads, electricity and security because investors needed a conducive environment before committing capital.

 

“We needed to create the enabling environment, ensure that roads are built, ensure that security is put in place and ensure that investors are protected by law,” he said.

https://www.aljazeera.com/news/2026/8/25/kremlin-adviser-warns-uk-drone-factories-could-face-attacks?traffic_source=rss

According to him, the approach had begun attracting investors from China, Brazil and Malaysia.

 

He said the ultimate objective was to create jobs and improve economic opportunities for Deltans.

By admin

We are Global Times Nigeria. We are an online newspaper, report about Nigerian politics, business and their leaders. We report deeply fairly and without fears or favors.

Leave a Reply